Earned Schedule (SPI(t) and Forecast Finish)
A DAX pattern for Earned Schedule: find the date your earned value was planned for, then get SPI(t), schedule variance in days, and a forecast finish date — the schedule metric that doesn't drift back to 1.0 on a late program.
Earned Schedule (SPI(t) and Forecast Finish)
Classic EVM measures schedule performance in money: SPI = EV / PV, and schedule variance in dollars. That has two well-known problems. "$137K behind schedule" doesn't say how late anything is. And near the end of a program, every planned dollar is due, so PV reaches BAC; once the work is finished EV reaches BAC too, and SPI returns to 1.0, even on a program that finished months late.
Earned Schedule, introduced by Walt Lipke in 2003, fixes both by measuring schedule in time. Instead of comparing today's EV with today's PV, it asks: on what date was the plan supposed to have earned this much?
ES Earned Schedule - the date the baseline planned to reach today's EV
AT Actual Time - today, the status date
PD Planned Duration - baseline start to planned finish
SPI(t) = ES / AT schedule efficiency, in time
SV(t) = ES - AT days ahead (+) or behind (-)
IEAC(t) = PD / SPI(t) forecast duration at the current paceAnatomy of Earned Schedule
The EVM dashboard tutorial's baseline PV curve, status as of May 15, 2026.
SPI (money)
0.64
SPI(t) = ES ÷ AT
0.69
SV(t)
-41 days
Forecast finish
Nov 2
plan: Jul 31
The baseline — cumulative PV for every day, from $0 on Jan 1 to the full $525K budget on Jul 31. By the status date the plan called for $378K.
Today's EV — the work actually done is worth $242K. Instead of comparing it with today's PV (that's SPI), slide it left along the curve.
Earned Schedule — the curve reaches $242K on Apr 4 (day 92.6). That's the date this much work was planned to be done by, interpolated between the two days either side.
The gap is in days — 41 days behind (SV(t)), and at that pace the 211-day plan takes about 305 days, finishing around Nov 2. Money-based SV can only say $137K of work is missing.
What You Need
The same two things the EVM dashboard tutorial already has:
- A time-phased PV measure: planned value as of whatever date is in context. The tutorial's
PV (Planned Value)measure readsMAX(DimDate[Date])from a disconnected date table, so evaluating it on each date traces the baseline S-curve. - An EV measure for the status date.
No new tables are needed.
Finding the Earned Schedule Date
ES Date =
VAR EarnedValue = [EV (Earned Value)]
VAR Curve =
ADDCOLUMNS(ALL(DimDate[Date]), "@PV", [PV (Planned Value)])
VAR LastDate =
MAXX(FILTER(Curve, [@PV] <= EarnedValue), DimDate[Date])
VAR PVAtLast =
MAXX(FILTER(Curve, DimDate[Date] = LastDate), [@PV])
VAR PVNext =
MAXX(FILTER(Curve, DimDate[Date] = LastDate + 1), [@PV])
RETURN
LastDate
+ IF(
ISBLANK(PVNext),
0,
DIVIDE(EarnedValue - PVAtLast, PVNext - PVAtLast, 0)
)How it works:
Curveevaluates the PV measure once for every date in the calendar.ALL(DimDate[Date])ignores the status-date slicer, and because[PV (Planned Value)]is a measure, each row gets context transition: its own date becomes the filter, soMAX(DimDate[Date])inside the PV measure returns that row's date.LastDateis the last date whose planned value doesn't exceed today'sEV. The PV curve never goes down, so that's the point where the plan "was" when it had earned this much.- The last two lines interpolate within the next day, so ES isn't stuck on whole days. This is the standard Earned Schedule formula,
ES = C + (EV − PV_C) / (PV_C+1 − PV_C), with daily periods.
On the tutorial's data, EV is $241,500. The plan had earned $239,013 by April 3 and $243,226 by April 4, so ES Date is April 3 plus 0.59 of a day.
SPI(t), SV(t), and the Forecast Finish
Project Start =
MIN(Tasks[PlannedStart])
Planned Finish =
MAX(Tasks[PlannedEnd])
ES (Days) =
CONVERT([ES Date] - [Project Start], DOUBLE)
AT (Days) =
CONVERT(MAX(DimDate[Date]) - [Project Start], DOUBLE)
SPI(t) =
DIVIDE([ES (Days)], [AT (Days)])
SV(t) (Days) =
[ES (Days)] - [AT (Days)]
IEAC(t) (Days) =
DIVIDE(CONVERT([Planned Finish] - [Project Start], DOUBLE), [SPI(t)])
Forecast Finish =
[Project Start] + [IEAC(t) (Days)]CONVERT(..., DOUBLE) matters: subtracting two dates in DAX gives a date/time value, not a number of days, so without it ES (Days) would display as a date in 1900. See TODAY() & NOW() for the same gotcha. Format ES Date and Forecast Finish as dates.
AT (Days) reads the status date the same way the PV measure does, from MAX(DimDate[Date]), so it needs the same status-date slicer.
| Measure | Tutorial value (May 15) |
|---|---|
SPI (money) | 0.64 |
ES (Days) | 92.6 (about April 4) |
AT (Days) | 134 |
SPI(t) | 0.69 |
SV(t) (Days) | −41 |
IEAC(t) (Days) | 305, against a 211-day plan |
Forecast Finish | November 2, 2026, against July 31 |
Why SPI(t) Doesn't Drift Back to 1.0
Run the tutorial program forward to a late finish: everything done on October 31, three months after the July 31 plan.
At completion: EV = BAC = $525,000 PV = BAC = $525,000
SPI = EV / PV = 1.00 looks perfect
SPI(t) = ES / AT = 211 / 303 = 0.70
SV(t) = ES - AT = -92 days the actual delayOnce the planned finish date has passed, PV is stuck at BAC, so money-based SPI can only climb back toward 1.0 as the remaining work gets done. ES can never exceed the planned duration, but AT keeps growing, so SPI(t) keeps reporting the delay all the way to the end.
Earned Schedule and Monte Carlo Answer Different Questions
Both produce a finish date, and they're easy to confuse:
| Earned Schedule forecast | Monte Carlo P80 | |
|---|---|---|
| Based on | Performance so far (EV against the baseline) | Three-point estimates and the task network |
| Answers | Where does the pace so far lead? | How likely is each finish date, given the estimates? |
| Available | Once work has started | Before work starts, and at any re-plan |
| Blind spot | Assumes today's pace continues; ignores which tasks are left | Only as good as the estimates; knows nothing about actual progress |
They're most useful together. Put the Earned Schedule forecast into the Schedule Risk Simulator as its target finish date, using the same baseline estimates. If only a small share of runs finish that late, actual performance is outside what the estimates allowed for, and the original P80 is too optimistic: re-estimate the remaining work and simulate again.
Common Mistakes
Computing ES From PV at Month Ends Without Interpolating
With monthly status, it's tempting to report ES as "the last month whose PV we've passed." That rounds every result down by up to a month. Interpolate between the two periods either side, as ES Date does; on the tutorial's data, interpolating between the March 31 and April 30 month-end values gives the same 92.6 days as the daily curve.
Letting the Status-Date Slicer Filter the Curve
The curve has to cover the whole baseline, not just the dates up to the status date. That's what ALL(DimDate[Date]) is for. Filtering the curve to dates before the status date gives the right answer only while you're behind schedule, and caps ES at today if you're ahead.
Using a Baseline That Keeps Moving
ES measures progress against the baseline PV curve. If the baseline is re-planned every month, ES measures progress against the latest re-plan, and a program can stay "on schedule" forever. Keep the baseline fixed, and treat a re-baseline as a deliberate, recorded event.
Treating IEAC(t) as a Commitment
PD / SPI(t) assumes the schedule efficiency so far continues unchanged, just as BAC / CPI does for cost. It's an early warning, not a plan. For a finish-date range that accounts for task uncertainty and merge points, see Monte Carlo schedule risk.
Best Practices
- Report
SPI(t)andSV(t) (Days)alongsideSPIandSV, especially in the last third of a program, when money-based SPI stops being informative. - Keep the PV curve on a fixed baseline, and evaluate it over the whole calendar with
ALL, not just up to the status date. - Format
SV(t)as days andForecast Finishas a date: schedule answers are more useful in schedule units. - Check
ES Dateby hand once: find the two dates whose PV brackets today's EV, and confirm ES lands between them.
Next Steps
- EVM Calculator — paste your cumulative PV baseline and status date to get ES, SPI(t), and a forecast finish, plus these measures as DAX
- Build an EVM Dashboard — the full model these measures run on
- Earned Value Management (EVM) Metrics
- Build a Monte Carlo Schedule Risk Dashboard
- ADDCOLUMNS() vs SELECTCOLUMNS()
- CALCULATE and context transition
Earned Value Management (EVM) Metrics
Ready-made DAX patterns for Planned Value, Earned Value, Actual Cost, CPI, SPI, and the standard EAC/VAC/TCPI forecasting measures used in program and systems engineering status reporting.
Risk Score & Heat Map
Ready-made DAX patterns for finding each item's latest assessment, computing a likelihood x impact risk score with threshold bands, and turning a disconnected-axis matrix into an actual heat map.