Build an Earned Value Management (EVM) Dashboard in Power BI
An end-to-end tutorial for systems and program engineers: turn a task list into real CPI, SPI, and EAC measures in DAX, using a disconnected date table to project planned value over time.
Most Power BI tutorials build a sales report. This one builds something systems and program engineers actually need: an Earned Value Management dashboard — the standard framework (PV, EV, AC, CPI, SPI, EAC) program offices use to answer one question honestly: is this program on budget and on schedule, and if not, by how much?
Task List (planned dates, budget, % complete, actual cost)
|
| DAX: PV, EV, AC measures
|
CPI, SPI, EAC, VAC — the standard EVM metric set
|
Dashboard (S-curve, variance table, status cards)Download program_status.csv — or paste the task list below directly into a .csv file yourself, both work identically. Every EVM formula used is shown in full, not just referenced.
What You're Building
A one-page program status dashboard answering the four questions an EVM review actually asks:
- Are we over or under budget for the work completed so far? (CPI)
- Are we ahead of or behind schedule? (SPI)
- If current performance continues, what will this program actually cost? (EAC)
- Which specific tasks are driving the variance?
+------------------------------------------------------------+
| CPI | SPI | Cost Variance | Schedule Variance |
+------------------------------------------------------------+
| PV / EV / AC over time (the classic EVM "S-curve") |
+------------------------------------------------------------+
| Task-level table: BAC, % Complete, EV, AC, CV, SV |
+------------------------------------------------------------+Step 1: The Raw Data
A program's task list, with the fields an EVM analysis actually needs: a planned start and end date per task (the baseline schedule), a budgeted cost, and — as of the current status date — how complete each task is and what's actually been spent.
TaskID,TaskName,PlannedStart,PlannedEnd,BAC,PercentComplete,ActualCost
1,Requirements Analysis,2026-01-01,2026-02-15,45000,1.00,42000
2,System Architecture,2026-01-15,2026-03-15,60000,0.90,58000
3,Subsystem A Design,2026-02-15,2026-04-30,80000,0.65,58000
4,Subsystem B Design,2026-02-15,2026-04-30,75000,0.55,50000
5,Integration Planning,2026-03-01,2026-04-15,30000,0.40,15000
6,Prototype Build,2026-04-01,2026-06-30,120000,0.20,30000
7,Verification & Test,2026-05-01,2026-07-31,90000,0.05,5000
8,Documentation,2026-01-01,2026-07-31,25000,0.35,10000BAC (Budget at Completion) is each task's total planned cost. PercentComplete and ActualCost are as-of-today status values — in a real program these come from whoever owns each task, updated on a regular reporting cadence. Save this as program_status.csv.
Step 2: Clean and Type in Power Query
Open Power BI Desktop, Get Data > Text/CSV, point it at the file, then Transform Data.
#"Changed Type" = Table.TransformColumnTypes(
Source,
{
{"PlannedStart", type date},
{"PlannedEnd", type date},
{"BAC", type number},
{"PercentComplete", type number},
{"ActualCost", type number}
}
)That's the whole cleaning step — this table is already at the right grain (one row per task), so there's no splitting into a star schema the way a transactional dataset needs. See Transformations if any of these type conversions aren't familiar.
Step 3: Add a Disconnected Date Table
Time intelligence here works differently than a typical sales model. There's no fact table full of dated transactions — just a baseline schedule (PlannedStart/PlannedEnd per task) and a single current status snapshot (PercentComplete, ActualCost). To plot Planned Value as a curve over time, the model needs a date table — but not related to the task table by a foreign key, since there's no Date column on a task to join against.
DimDate =
CALENDAR(DATE(2026, 1, 1), DATE(2026, 7, 31))Leave it unrelated to the task table. This is a disconnected table — a deliberate modeling choice, not a mistake. See Date Tables for the general pattern; the difference here is that this date table drives a projection (see Step 4), not a join.
Step 4: Write the EVM Measures
Create a dedicated measures table (Modeling > New Table) to keep these separate from the task data. See Measures for why a dedicated measures table is worth doing.
Planned Value (PV)
PV (Planned Value) =
SUMX(
Tasks,
Tasks[BAC] *
MIN(
1,
MAX(
0,
DIVIDE(
MAX(DimDate[Date]) - Tasks[PlannedStart],
Tasks[PlannedEnd] - Tasks[PlannedStart]
)
)
)
)This is the technique that makes the disconnected DimDate useful: MAX(DimDate[Date]) reads whatever date is currently in context — a single day on a chart's x-axis, or the latest date under a slicer — and computes what fraction of each task's baseline duration has elapsed by that date. MIN(1, MAX(0, ...)) clamps that fraction between 0% (before the task starts) and 100% (after it ends), so each task contributes its full BAC once its planned end date has passed, and nothing before its planned start.
Earned Value (EV) and Actual Cost (AC)
EV (Earned Value) =
SUMX(Tasks, Tasks[BAC] * Tasks[PercentComplete])
AC (Actual Cost) =
SUM(Tasks[ActualCost])
BAC (Budget at Completion) =
SUM(Tasks[BAC])Unlike PV, these aren't projected across time — PercentComplete and ActualCost are only known as of the last status update, not for every day in between. A real program tracks these historically too (a snapshot per reporting period), which would let EV/AC plot as curves the same way PV does; this tutorial keeps to a single current snapshot to stay focused on the core formulas.
Variances
CV (Cost Variance) =
[EV (Earned Value)] - [AC (Actual Cost)]
SV (Schedule Variance) =
[EV (Earned Value)] - [PV (Planned Value)]CV negative -> spent more than the value earned (over budget)
SV negative -> earned less value than planned by this point (behind schedule)CPI and SPI
CPI (Cost Performance Index) =
DIVIDE([EV (Earned Value)], [AC (Actual Cost)])
SPI (Schedule Performance Index) =
DIVIDE([EV (Earned Value)], [PV (Planned Value)])CPI < 1 -> over budget for the work completed
CPI > 1 -> under budget for the work completed
SPI < 1 -> behind schedule
SPI > 1 -> ahead of scheduleEAC, ETC, VAC, and TCPI
EAC (Estimate at Completion) =
DIVIDE([BAC (Budget at Completion)], [CPI (Cost Performance Index)])
ETC (Estimate to Complete) =
[EAC (Estimate at Completion)] - [AC (Actual Cost)]
VAC (Variance at Completion) =
[BAC (Budget at Completion)] - [EAC (Estimate at Completion)]
TCPI (To-Complete Performance Index) =
DIVIDE(
[BAC (Budget at Completion)] - [EV (Earned Value)],
[BAC (Budget at Completion)] - [AC (Actual Cost)]
)EAC here uses the simplest standard formula — it assumes the program's cost efficiency so far (CPI) continues unchanged for the remaining work. TCPI answers a different question: given what's actually been spent, how efficiently does the remaining work need to be performed to still hit the original BAC? A TCPI well above 1 is a sign that the original budget is no longer realistic.
Step 5: Lay Out the Report
Page: "Program Status"
Status date (slicer):
Field: DimDate[Date], style "Before", set to 2026-05-15
Edit interactions: filters the cards and the table, not the S-curve
Row 1 (KPI cards):
[CPI (Cost Performance Index)] [SPI (Schedule Performance Index)]
[CV (Cost Variance)] [SV (Schedule Variance)]
Row 2 (line chart, the S-curve):
X-axis: DimDate[Date]
Y-axis: [PV (Planned Value)]
Reference line or card: current [EV (Earned Value)] and [AC (Actual Cost)]
Row 3 (table):
Columns: Tasks[TaskName], Tasks[BAC], Tasks[PercentComplete],
[EV (Earned Value)], [AC (Actual Cost)],
[CV (Cost Variance)], [SV (Schedule Variance)]
Conditional formatting: CV and SV columns, red below zeroThe status-date slicer is what makes the cards mean "as of today". PV reads MAX(DimDate[Date]), and with no date filter that's the last date in the calendar, July 31, by which point every task's planned work is fully due. PV would equal BAC ($525,000) and SPI would drop to 0.46. Setting the slicer to May 15 makes MAX(DimDate[Date]) return May 15, so PV is $378,390. Turning off the slicer's interaction with the line chart (Format > Edit interactions) keeps the S-curve showing the whole schedule.
With this dataset (status as of mid-May against a program running January through July), the numbers tell a specific, realistic story: CPI lands around 0.90 and SPI around 0.64 — a program that's both over budget and significantly behind schedule, with TCPI climbing above 1.10 as a result. That combination (both indices below 1) is exactly the pattern an EVM dashboard exists to surface early, before it shows up as a missed milestone.
Anatomy of an EVM status report
This tutorial's task list, status as of May 15, 2026. Plan % is how far each task is through its baseline dates by then.
| Task | BAC | Plan % | Done % | Plan / Done % | PV | EV | AC |
|---|---|---|---|---|---|---|---|
| ReqsRequirements Analysis | $45K | 100% | 100% | 100/100 | $45K | $45K | $42K |
| ArchitectureSystem Architecture | $60K | 100% | 90% | 100/90 | $60K | $54K | $58K |
| Subsys ASubsystem A Design | $80K | 100% | 65% | 100/65 | $80K | $52K | $58K |
| Subsys BSubsystem B Design | $75K | 100% | 55% | 100/55 | $75K | $41K | $50K |
| IntegrationIntegration Planning | $30K | 100% | 40% | 100/40 | $30K | $12K | $15K |
| PrototypePrototype Build | $120K | 49% | 20% | 49/20 | $59K | $24K | $30K |
| V&TVerification & Test | $90K | 15% | 5% | 15/5 | $14K | $5K | $5K |
| DocsDocumentation | $25K | 64% | 35% | 64/35 | $16K | $9K | $10K |
| Program total | $525K | $378K | $242K | $268K |
1Planned Value
$378,390
Σ BAC × Planned %
2Earned Value
$241,500
Σ BAC × Complete %
3Actual Cost
$268,000
Σ ActualCost
✓Everything else is derived from those three
CPI = EV ÷ AC
0.90
over budget
SPI = EV ÷ PV
0.64
behind schedule
CV = EV − AC
−$26,500
neutral at 0, not 1
SV = EV − PV
−$136,890
neutral at 0, not 1
EAC = BAC ÷ CPI
$582,609
vs. BAC $525,000
PV — what the plan said each task should be worth by now. Prototype Build is only 49% of the way through its planned dates, so it contributes $58,667, not its full $120,000.
EV — earned per task, then summed with SUMX. Multiplying the total BAC by the average percent complete instead gives $269,063, $27,563 too optimistic, because the two big late-stage tasks, Prototype Build and Verification & Test, are the least complete.
AC — the only one of the three that comes straight from the ledger, with no percentages involved.
Derived metrics — every ratio and variance compares two of the colored totals above. CPI 0.90 means each dollar spent has earned about 90¢ of planned work; carried forward, that turns a $525,000 budget into a $582,609 forecast.
See Charts and Tables for configuring these visual types, and Conditional Formatting for the red/green variance treatment.
Step 6: Add Earned Schedule
SPI of 0.64 says the program is behind, and SV says by $137K. Neither says by how many days, and the program manager will be asked exactly that. Earned Schedule answers it with the model you already have: find the date on the baseline S-curve where planned value equals today's EV.
ES Date =
VAR EarnedValue = [EV (Earned Value)]
VAR Curve =
ADDCOLUMNS(ALL(DimDate[Date]), "@PV", [PV (Planned Value)])
VAR LastDate =
MAXX(FILTER(Curve, [@PV] <= EarnedValue), DimDate[Date])
VAR PVAtLast =
MAXX(FILTER(Curve, DimDate[Date] = LastDate), [@PV])
VAR PVNext =
MAXX(FILTER(Curve, DimDate[Date] = LastDate + 1), [@PV])
RETURN
LastDate
+ IF(
ISBLANK(PVNext),
0,
DIVIDE(EarnedValue - PVAtLast, PVNext - PVAtLast, 0)
)
Project Start =
MIN(Tasks[PlannedStart])
Planned Finish =
MAX(Tasks[PlannedEnd])
ES (Days) =
CONVERT([ES Date] - [Project Start], DOUBLE)
AT (Days) =
CONVERT(MAX(DimDate[Date]) - [Project Start], DOUBLE)
SPI(t) =
DIVIDE([ES (Days)], [AT (Days)])
SV(t) (Days) =
[ES (Days)] - [AT (Days)]
IEAC(t) (Days) =
DIVIDE(CONVERT([Planned Finish] - [Project Start], DOUBLE), [SPI(t)])
Forecast Finish =
[Project Start] + [IEAC(t) (Days)]Curve evaluates the PV measure for every date in the calendar (ALL ignores the status-date slicer, and the measure reference gives each row its own date), and ES Date is the last date whose planned value hasn't passed today's EV, plus a fraction of the next day. Format ES Date and Forecast Finish as dates. CONVERT(..., DOUBLE) turns date differences into plain numbers of days.
With the status date on May 15:
EV = $241,500, which the plan expected by April 3-4 -> ES = 92.6 days
Status date May 15 -> AT = 134 days
SPI(t) = 92.6 / 134 = 0.69
SV(t) = 92.6 - 134 = -41 days
Forecast finish = 211 / 0.69 = 305 days -> November 2, 2026 (plan: July 31)Add SPI(t), SV(t) (Days), and Forecast Finish as cards next to CPI and SPI. The headline changes from "$137K behind" to "about six weeks behind, heading for early November", which is the version people act on.
Anatomy of Earned Schedule
This tutorial's baseline PV curve, status as of May 15, 2026.
SPI (money)
0.64
SPI(t) = ES ÷ AT
0.69
SV(t)
-41 days
Forecast finish
Nov 2
plan: Jul 31
The baseline — cumulative PV for every day, from $0 on Jan 1 to the full $525K budget on Jul 31. By the status date the plan called for $378K.
Today's EV — the work actually done is worth $242K. Instead of comparing it with today's PV (that's SPI), slide it left along the curve.
Earned Schedule — the curve reaches $242K on Apr 4 (day 92.6). That's the date this much work was planned to be done by, interpolated between the two days either side.
The gap is in days — 41 days behind (SV(t)), and at that pace the 211-day plan takes about 305 days, finishing around Nov 2. Money-based SV can only say $137K of work is missing.
SPI(t) matters most late in a program. If this one finishes everything on October 31, SPI will read a perfect 1.00 (every planned dollar is earned), while SPI(t) still reads 0.70 and SV(t) −92 days. See Earned Schedule for the pattern on its own.
Common Mistakes
Computing EV as a Single Program-Wide Percentage
Multiplying total program budget by an overall "percent complete" produces a number that looks like EV but isn't — EVM is computed per task, then summed. A program that's 100% done on cheap tasks and 0% done on expensive ones is nowhere near 50% complete in EV terms, even if a naive average says so.
Reading SPI as a Measure of Time
SPI compares the value of work completed with the value planned, not dates. At completion EV reaches BAC and so does PV, so SPI drifts back to 1.0 even on a program that finished months late; and work done early on non-critical tasks can hold SPI up while the critical path slips. Report SPI(t) from Step 6 alongside it, and check the schedule itself.
Leaving the Status Date Unset
Without a date filter, MAX(DimDate[Date]) returns the last day of the calendar, so every task counts as fully planned and PV equals BAC. EV, AC and CPI don't depend on the date, so they still look right, which makes the wrong SPI and SV easy to miss. Always set the status date to the date the PercentComplete and ActualCost values were reported.
Treating a Single EAC Formula as Definitive
EAC = BAC / CPI is the simplest standard formula, but it's one of several (others weight in SPI, or let managers substitute a bottom-up re-estimate). Treat it as a data point that starts a conversation, not a number to report as certain.
Tutorial Checklist
- Task data has one row per task with a planned start, planned end, budget, percent complete, and actual cost.
DimDateexists as a continuous calendar but is not related to the task table — it's used to projectPV, not to join.PVis computed per task and clamped between 0% and 100% of that task's baseline duration before summing.EVandACare computed per task then summed — never as a single program-wide percentage.- A status-date slicer sets
MAX(DimDate[Date])for the cards and table, soPVandSPIare as of the reporting date, not the end of the calendar. CPI,SPI, andEAChave been sanity-checked against the underlyingBAC/EV/AC/PVnumbers, not just trusted at face value.SPI(t)andSV(t)are reported alongsideSPI, withES Datechecked by hand against the two PV values that bracket today'sEV.
Next Steps
- EVM Calculator — enter BAC, PV, EV, and AC from any status report and get every metric in this tutorial, with three EAC methods compared.
- Build a Monte Carlo Schedule Risk Dashboard in Power BI — SPI says how far behind you are today; this follow-on tutorial simulates the same eight tasks 10,000 times to show how likely each finish date is, using the same disconnected-date pattern as PV here.
- Schedule Risk Simulator — paste any task network with three-point estimates to get P50/P80 finish dates and an S-curve without building a model.
- Earned Value Management (EVM) Metrics — a fast reference for these same PV/EV/AC/CPI/SPI/EAC measures, including the other standard EAC formula variants.
- Date Tables — the general pattern behind Step 3's calendar table.
- CALCULATE — for filtering these measures to a specific task, phase, or program.
- DAX CALCULATE Modifiers Cheat Sheet — useful once this model needs a "percent of total budget" style measure.
- Row-Level Security — restricting each program manager to their own set of tasks.
See the same disconnected-table technique used for a 5x5 grid instead of a timeline: Build a Risk Register and Risk Matrix Dashboard.
FAQ
+What is CPI in Earned Value Management?
Cost Performance Index = Earned Value divided by Actual Cost. A CPI below 1 means the work performed so far cost more than it was budgeted for.
+What is SPI in Earned Value Management?
Schedule Performance Index = Earned Value divided by Planned Value. An SPI below 1 means less work has been completed than was planned by this point in the schedule.
+What's the difference between EAC and BAC?
BAC (Budget at Completion) is the original total budget. EAC (Estimate at Completion) is a revised total-cost forecast based on how the program is actually performing, calculated as BAC divided by CPI in its simplest form.
+Can Power BI calculate EVM metrics without dedicated project management software?
Yes. Every metric in this tutorial — PV, EV, AC, CPI, SPI, EAC — is a standard DAX measure built from a task list with planned dates, budgeted cost, percent complete, and actual cost. No specialized PM tool is required.