EVM Calculator
Four numbers from your status report, and the full earned value picture: cost and schedule performance, where the program will land, and how much better the remaining work has to go to hit the budget. Then take the same metrics into Power BI as DAX.
Status as of your reporting date
Pre-filled with the status-date numbers from the EVM dashboard tutorial. Any currency works; amounts are shown with $ for readability.
Over budget and behind schedule for the work completed so far.
CPI
0.90
Each $1 spent earned $0.90 of planned work.
SPI
0.64
Work is being done at 64% of the planned rate.
Cost variance
-$26,500
Spent more than the completed work is worth.
Schedule variance
-$136,890
Value of planned work not yet done.
EAC
$582,609
Forecast total cost at completion.
ETC
$314,609
Still to spend from today.
VAC
-$57,609
Forecast overrun against BAC.
TCPI
1.10
The rest must run 10% more efficiently to hit BAC.
Earned Schedule: how late, in days
SPI says how far behind you are in money. Earned Schedule finds the date your baseline planned to reach today's EV, so the answer comes out in days, and it doesn't drift back to 1.0 at the end of a late program. Uses the EV above. How it works.
Earned schedule
Apr 4, 2026
Day 92.6: when the plan expected today's EV.
SPI(t)
0.69
ES ÷ AT. SPI in money is 0.64.
SV(t)
-41 days
Behind the plan, 134 days in.
Forecast finish
Nov 2, 2026
Plan: Jul 31, 2026. Assumes today's pace continues.
The same measures in DAX, on the tutorial's daily PV measure and disconnected date table.
ES Date =
VAR EarnedValue = [EV (Earned Value)]
VAR Curve =
ADDCOLUMNS(ALL(DimDate[Date]), "@PV", [PV (Planned Value)])
VAR LastDate =
MAXX(FILTER(Curve, [@PV] <= EarnedValue), DimDate[Date])
VAR PVAtLast =
MAXX(FILTER(Curve, DimDate[Date] = LastDate), [@PV])
VAR PVNext =
MAXX(FILTER(Curve, DimDate[Date] = LastDate + 1), [@PV])
RETURN
LastDate
+ IF(
ISBLANK(PVNext),
0,
DIVIDE(EarnedValue - PVAtLast, PVNext - PVAtLast, 0)
)
Project Start =
MIN(Tasks[PlannedStart])
Planned Finish =
MAX(Tasks[PlannedEnd])
ES (Days) =
CONVERT([ES Date] - [Project Start], DOUBLE)
AT (Days) =
CONVERT(MAX(DimDate[Date]) - [Project Start], DOUBLE)
SPI(t) =
DIVIDE([ES (Days)], [AT (Days)])
SV(t) (Days) =
[ES (Days)] - [AT (Days)]
IEAC(t) (Days) =
DIVIDE(CONVERT([Planned Finish] - [Project Start], DOUBLE), [SPI(t)])
Forecast Finish =
[Project Start] + [IEAC(t) (Days)]The same metrics as DAX measures
Built on the PV, EV, AC, and BAC measures from the tutorial, using the EAC you picked. Paste each one into New measure.
CV (Cost Variance) =
[EV (Earned Value)] - [AC (Actual Cost)]
SV (Schedule Variance) =
[EV (Earned Value)] - [PV (Planned Value)]
CPI (Cost Performance Index) =
DIVIDE([EV (Earned Value)], [AC (Actual Cost)])
SPI (Schedule Performance Index) =
DIVIDE([EV (Earned Value)], [PV (Planned Value)])
EAC (Estimate at Completion) = -- BAC / CPI
DIVIDE([BAC (Budget at Completion)], [CPI (Cost Performance Index)])
ETC (Estimate to Complete) =
[EAC (Estimate at Completion)] - [AC (Actual Cost)]
VAC (Variance at Completion) =
[BAC (Budget at Completion)] - [EAC (Estimate at Completion)]
TCPI (To-Complete Performance Index) =
DIVIDE(
[BAC (Budget at Completion)] - [EV (Earned Value)],
[BAC (Budget at Completion)] - [AC (Actual Cost)]
)Free, with no sign-in and no request limit. Everything runs in your browser, and nothing you type is sent anywhere.
One snapshot isn't a trend. CPI and SPI are most useful tracked period over period, and SPI drifts back toward 1.0 near the end of any program as the remaining planned work runs out, even a late one. That's what the Earned Schedule section is for: SPI(t) keeps reporting the delay. The EVM dashboard tutorial builds these as measures over a task list so you can watch them move.
For the formulas on their own, see Earned Value Management (EVM) Metrics, or browse all the Power BI tools.