Schedule Risk Simulator

Give each task a best case, a most-likely case, and a worst case, and a Monte Carlo simulation runs the schedule thousands of times to show how likely each finish date really is. Then take the runs into Power BI with the DAX for an S-curve and P80 card.

Distribution
Durations
Iterations

Adding up the most-likely durations finishes on Sep 16, 2026, but only 9% of 10,000 simulated runs finished by then. For 80% confidence, plan on Oct 20, 2026: 34 calendar days of schedule reserve.

Plan date

2026-09-16

Most-likely durations, 255 days. 9% chance.

P50

2026-10-06

Half the runs finished by this date.

P80

2026-10-20

A common commitment level.

P90

2026-10-27

One run in ten finished later.

Probability of finishing by each dateThe S-curve of every simulated finish. Hover to read any date. The dashed line is the plan date; the solid line is P80.
0%25%50%75%100%Sep 26Oct 26Nov 26Dec 26PlanP80

Which tasks drive the finish?

The criticality index is the share of runs in which a task was on the critical path. Parallel paths split it between them, and that's why the plan date is optimistic: the project waits for whichever branch runs late. Plan marks the critical path when every task takes its most-likely duration.

TaskMeanCriticality
1 Requirements AnalysisPlan41.6
100%
2 System ArchitecturePlan47.6
100%
6 Prototype BuildPlan64.1
100%
7 Verification & TestPlan53.4
>99%
4 Subsystem B DesignPlan64.2
52%
3 Subsystem A DesignPlan63.3
48%
8 Documentation30.9
<1%
5 Integration Planning25.8
0%

Take it into Power BI

DAX can't walk a task network, so run the simulation here and load the runs as a table. Download both files, then Get data > Text/CSV. The measures below reproduce every number on this page from them.

The S-curve is the same disconnected-date pattern the EVM tutorial uses for planned value. For a fuller calendar, use the Date Table Generator.

-- Load schedule_simulations.csv as a table named Simulations
-- (FinishDate as Date) and schedule_tasks.csv as Tasks.

-- Disconnected calendar for the S-curve and the target-date slicer.
-- New table; don't relate it to Simulations.
FinishCalendar =
CALENDAR (
    MIN ( Simulations[FinishDate] ) - 14,
    MAX ( Simulations[FinishDate] ) + 14
)

Simulated Runs = COUNTROWS ( Simulations )

-- Share of runs finished on or before the date in context: the S-curve on a
-- line chart with FinishCalendar[Date] on the axis, or the on-time
-- probability on a card when a slicer picks one date.
Probability Finished By =
VAR StatusDate = MAX ( FinishCalendar[Date] )
RETURN
    DIVIDE (
        COUNTROWS ( FILTER ( Simulations, Simulations[FinishDate] <= StatusDate ) ),
        [Simulated Runs]
    )

-- Fixed-date version for a KPI card, no slicer needed.
Probability On Target =
VAR TargetDate = DATE ( 2026, 9, 16 )
RETURN
    DIVIDE (
        COUNTROWS ( FILTER ( Simulations, Simulations[FinishDate] <= TargetDate ) ),
        [Simulated Runs]
    )

P50 Finish = CONVERT ( ROUNDUP ( PERCENTILEX.INC ( Simulations, Simulations[FinishDate] * 1, 0.5 ), 0 ), DATETIME )

P80 Finish = CONVERT ( ROUNDUP ( PERCENTILEX.INC ( Simulations, Simulations[FinishDate] * 1, 0.8 ), 0 ), DATETIME )

P90 Finish = CONVERT ( ROUNDUP ( PERCENTILEX.INC ( Simulations, Simulations[FinishDate] * 1, 0.9 ), 0 ), DATETIME )

-- Schedule reserve needed to reach 80% confidence over the plan date.
P80 Buffer Days = DATEDIFF ( DATE ( 2026, 9, 16 ), [P80 Finish], DAY )

-- For a bar chart of Tasks[TaskName]: how often each task drove the finish.
Criticality Index = AVERAGE ( Tasks[CriticalityIndex] )

Free, with no sign-in and no request limit. Everything runs in your browser, and nothing you paste is sent anywhere. Results use a fixed random seed, so the same inputs give the same numbers; Re-run draws a fresh set.

Why the plan date is usually late. Two things push the simulated finish past the sum of most-likely durations. Estimates are skewed: a task can slip much further than it can gain. And wherever parallel paths merge, the next task waits for whichever one finishes last, so the merge point inherits the worst of both. That's merge bias, and it's why the most-likely plan often has well under a 50% chance.

Beta-PERT or triangular? Beta-PERT weights the most-likely value more heavily, with a mean of (O + 4M + P) / 6. Triangular gives the tails more weight and makes a more pessimistic forecast from the same three numbers.

To build the simulation inside Power BI itself, with RAND() and BETA.INV in a calculated table, follow the Monte Carlo schedule risk tutorial. Its percentile and S-curve measures read this tool's runs CSV unchanged.

Checking an Earned Schedule forecast. Once work is under way, the Earned Schedule forecast says where the pace so far leads. Enter that date as the target finish here, with the same baseline estimates. If only a few percent of runs finish that late, the program is running worse than its estimates allowed for: re-estimate the remaining tasks rather than trusting the original P80.

SPI from the EVM dashboard tutorial tells you how far behind a program is today; this tells you how likely each finish is. Try the EVM Calculator for the status side, or browse all the Power BI tools.